Quyết định 699/QD-TTg

Decision No. 699/QD-TTg of August 23, 2002, approving the planning on development and renovation of Ho Chi Minh city's power network in the 2002-2010 period, with the prospect till 2020 taken into account

Nội dung toàn văn Decision No. 699/QD-TTg of August 23, 2002, approving the planning on development and renovation of Ho Chi Minh city's power network in the 2002-2010 period, with the prospect till 2020 taken into account


THE GOVERNMENT
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence- Freedom- Happiness
------------

No.699/QD-TTg

Hanoi, August 23, 2002

 

DECISION

APPROVING THE PLANNING ON DEVELOPMENT AND RENOVATION OF HO CHI MINH CITY'S POWER NETWORK IN THE 2002-2010 PERIOD, WITH THE PROSPECT TILL 2020 TAKEN INTO ACCOUNT

THE PRIME MINISTER

Pursuant to the Law on Organization of the Government dated December 25, 2001;
At the proposal of the Ministry of Industry (Official Dispatch No. 2733/CV-KHDT dated July 22, 2002); and proceeding from the opinions of the concerned ministries and branches regarding the approval of the planning on renovation and development of Ho Chi Minh City's power network in the 2001-2010 period, with the prospect till 2020 taken into account,

DECIDES:

Article 1. To approve the planning on development and renovation of Ho Chi Minh City's power network in the 2002-2010 period, with the prospect till 2020 taken into account (hereinafter referred to as Ho Chi Minh City's Electricity Planning for short) with the following principal contents:

1. On the load demand:

To steadily develop, raise the quality of, and fully satisfy the demand for load in service of people's daily life as well as socio-economic development, security and defense; to meet the requirements of the national industrialization and modernization, and ensure the achievement of the socio-economic development objectives till 2010 and the realization of the development orientation till 2020. The load demand is forecasts as follows:

- By 2005: The commercial electricity output shall reach 11.2 to 11.9 billion kWh with the maximum capacity of 2,180 to 2,310 MW. The average electricity growth rate in the 2002-2005 period shall be 14.1 to 15.4%/year. The per-capita electricity output shall reach 1,970 kWh/person/year.

- By 2010: The commercial electricity output is expected to reach 21.3 to 22.9 billion kWh with the maximum capacity of 3,900 to 4,270 MW. The average electricity growth rate in the 2006-2010 period shall be 13.6 to 14.1%/year. The per-capita electricity output shall reach 3,225 kWh/person/year.

- By 2020: According to the orientation, the commercial electricity output shall reach 48.4 to 57.3 billion kWh with the maximum capacity of 8,678 to 10,200 MW. The average electricity growth rate in the 2011-2020 period shall be 8.6 to 9.6 %/year. The per-capita electricity output shall reach 5,730 kWh/person/year.

2. On the renovation and development of the electric power network :

a) The renovation and development of Ho Chi Minh City's electric power network must satisfy the above-said load demand, with a back-up, and be made synchronously from high tension to low tension networks, thus overcoming the current state of unsafe, patchy and high-loss power grid.

b) Viewpoint and standards for designing the diagram of the city's power transmission and distribution networks shall be as follows:

- 220 and 110 kV networks: Shall be designed in loop circuits with every transformer station energized by two sources. The wire cross-section for aerial 220 or 110 kV power lines shall be ≥ 400 mm2, or ≥ 240 mm2 for phase-wire . In the inner city, 220 or 110 kV power lines shall be designed with two or more circuits, while at places with urban aesthetic requirements, underground copper-core cable with appropriate cross-sections and transformer stations furnished with modern technologies (GIS, compact) shall be installed.

- Medium-tension distribution network: Shall, according to the orientation, be converted into lines with the standard voltage of 22 kV. The network structure and its reliability shall be designed according to the following principle: Medium-tension lines shall be designed in loop circuits and energized from two 110kV transformer stations or two sectionalizing busbars of a 110 kV station; power lines in the city center and new urban quarters shall be laid underground. The outgoing feeders shall be protected by line-end breakers and load breakers on the axis at appropriate positions for sectionalizing purpose. The ramifications shall be protected by FCO or LBFCO at ramification ends.

- Low-tension networks: Shall use the low-voltage (220/380V) three-phase four-conductor system with one neutral earthing, or one-phase two-conductor system. Underground low-tension cable shall use XLPE conductor with a cross-section of 4 x 120 mm2 or 4 x 95 mm2 in main quarters and new urban areas with high urban aesthetic requirements. In other areas, aerial bundled cable (ABC) with a cross-section of 4 x 70 mm2, 4 x 95 mm2 or 4 x 120 mm2 shall be used.

c) Volumes of new construction and renovation of Ho Chi Minh City's electric power network by the planning phases shall be as follows:

- The 2002-2010 period:

+ 220 kV power line: 102 km shall be newly built.

+ 110 kV power line: about 284.7 km shall be newly built and 81 km shall be renovated.

+ 220 kV transformer stations: Five new transformer stations with a total output of 2,250 MVA shall be built, while six existing stations shall be renovated with the total additional output of 1,432 MVA.

+ 110 kV transformer stations: 32 new transformer stations with a total output of 2,492.6 MVA shall be built, while 36 existing stations shall be renovated with the total output of 2,403.6 MVA

+ Medium-tension distribution network: A new 22 - 15 kV line shall be built, including aerial line and underground cable with a total length of 1,940 km, while other 297 km, including 104 km of underground cable, shall be upgraded to 22 kV. To accelerate the underground installation of the medium-tension network, thus ensuring that by 2010 the underground rate reach 50%.

+ New consumption transformer stations shall be built with a total output of 2,984,717 kVA and existing ones shall be renovated with the total output of 1,097,854 kVA.

+4,873 km of low-tension lines shall be built.

Projects and works for renovating and developing the power transmission network in Ho Chi Minh City in the 2002-2010 period are on the list enclosed with the Appendix to this Decision. Particularly, the 220 kV network shall be in line with Vietnam's Electricity Development Planning (phase V of the electricity planning).

- Power network development works after 2010 shall be specifically identified when implementing Ho Chi Minh City's Electricity Planning for the subsequent period.

3. On the investment capital demand:

The total investment capital demanded for the renovation and development of Ho Chi Minh City's power network in the 2002-2010 period shall be VND 9,993.2 billion, of which VND 5,443.2 billion is demanded for the 2002-2005 period and VND 4,550 billion is demanded for the 2006-2010 period. Investment capital for the 2002-2010 period shall be distributed to networks of various power tensions as follows:

+ 220 kV network : VND 1,606.6 billion

+ 110 kV network : VND 3,292.6 billion

+ Medium-tension network : VND 3,862.7 billion

+ Low-tension network: VND 1,11 billion

+ Reactive power compensation for medium- and low- tension lines, equipment on networks and breakers: VND 120.3 billion.

The investment capital demand of the 220kV network or higher-tension networks shall be balanced within Vietnam's Electricity Development Planning, phase V; while in Ho Chi Minh City's Electricity Planning, the investment capital demand shall be considered for the 110kV network or lower-tension networks. The total investment capital demand for the 110 kV network and the medium- and low- tension distribution networks of the whole city in the 2002-2010 period shall be VND 8,386.6 billion, of which the capital already incorporated in plans shall be VND 1,601.4 billion.

4. On mechanisms:

Specific support mechanisms and policies shall be studied and promulgated on the basis of nature and demands of projects.

It is permitted to make feasibility study reports, skipping the stage of elaborating pre-feasibility study reports, for projects on the list of projects on development and renovation of the power transmission network in Ho Chi Minh City in the 2002-2010 period.

Article 2.- Organization of implementation

1. The Ministry of Industry:

a) To direct Vietnam Electricity Corporation and Ho Chi Minh City Electricity Company in implementing Ho Chi Minh City's Electricity Planning strictly according to the set plans and schedules. Cases beyond its competence shall be reported to the Prime Minister for consideration and decision.

b) To study and propose mechanisms and policies for implementation of Ho Chi Minh City's Electricity Planning according to its competence.

c) To regularly evaluate and update the electricity load demand, in order to adopt a rational electricity network development program which can satisfy the city's load demand after 2005. In case of great changes in the load demand, it shall have to take initiative in calculating and promptly readjusting and supplementing Ho Chi Minh City's Electricity Planning, then submit it to the Prime Minister for approval.

2. The People's Committee of Ho Chi Minh City:

a) To plan the allocation of land to projects on electricity transmission lines and transformer stations in line with the approved electricity planning.

b) To balance capital to investment projects on rural electrification or underground installation of electricity distribution networks of the inner city and new urban quarters according to the investment decentralization.

c) To coordinate with the concerned ministries and branches in synchronously planning the common technical infrastructure, particularly the city's underground works.

d) To direct the functional bodies in examining and handling acts of encroaching upon the power grid safety corridor, with a view to ensuring safety for people and minimizing incidents to the city's power grid.

3. Vietnam Electricity Corporation:

a) To be responsible for ensuring the stable and safe power supply, with higher and higher quality and better services, thus meeting socio-economic development demand and the people's daily life.

b) To mobilize and efficiently use all capital sources for investment in the renovation and development of the power grid according to mechanism of self-borrowing and self-repaying, and the realization of the mechanism whereby the central government, localities, the State and people jointly develop rural power networks in suburban districts; and modernize the power distribution network in the inner city and new urban quarters. To execute projects on the approved list for achievement of the objectives set forth in the planning according to the set schedule.

c) To base itself on the list of projects specified in the Appendix enclosed herewith to formulate and submit projects to competent authorities for approval according to the current regulations.

Article 3.- This Decision takes effect after its signing.

Article 4.- The Minister of Industry , the heads of the concerned ministries and branches, the president of the People's Committee of Ho Chi Minh City, the Managing Board and the general director of Vietnam Electricity Corporation shall have to implement this Decision.

 

FOR THE PRIME MINISTER
DEPUTY PRIME MINISTER




Nguyen Tan Dung

 

APPENDIX

LIST OF POWER LINE AND TRANSFORMER STATION PROJECTS IN THE 2002-2010 PERIOD IN HO CHI MINH CITY
(Issued together with the Prime Minister's Decision No. 699/QD-TTg dated August 23, 2002)

1. List of transformer stations:

Ordinal number

Names of projects

Output (MVA)

Tension (kV)

Commissioning year

 

A. 220 KV STATIONS

 

 

 

 

I. 2002-2005 period:

 

 

 

1

Raising of output of Phu Lam 220 kV station

2 x 125 --> 2 x 250

220/110

2002

2

Renovation of Thu Duc 220 kV station

2 x 3 x 28 + 125 --> 350 - 500

220/110

2003-2004

3

Construction of Cat Lai 220 kV station

2 x 250

220/110

2002-2003

4

Construction of Tao Dan 220 kV station (GIS)

1 x 250

220/110

2003-2004

5

Construction of Southern Sai Gon 220 kV station

2 x 250

220/110

2004-2005

 

II. 2006-2010 period (forecast):

 

 

 

1

Raising of output of Nha Be 220kV station

2 x 250 --> 3 x 250

220/110

2006

2

Raising of output of Tao Dan 220kV station

1 x 250 --> 2 x 250

220/110

2006-2007

3

Renovation and output-raising of Thu Duc 220 kV station

2 x 175 --> 2 x 250

220/110

2009

4

Raising of output of Southern Sai Gon 220kV station

2 x 250 --> 3 x 250

220/110

2009

5

Construction of Tan Binh 220 kV station

2 x 250

220/110

2006-2007

6

Construction of Binh Phuoc 220 kV station

2 x 250

220/110

2006-2007

 

B. 110 KV STATIONS

 

 

 

 

I. 2002-2005 period:

 

 

 

 

Renovation and output-raising projects:

 

 

 

1

Raising of output of Cu Chi station

1 x 25 --> 25 + 63

110/22-15

2002-2003

2

Raising of output of Northern Thu Duc station

40 + 63 --> 2 x 63

110/22-15

2003

3

Raising of output of An Nghia station

11.5 --> 25

110/22-15

2002

4

Raising of output of Phu Lam station

40 + 63 --> 2 x 63

110/22-15

2002

5

Raising of output of Hoc Mon station

40 + 63 --> 2 x 63

110/22-15

2002

6

Raising of output of Hung Vuong station

25 + 63 --> 2 x 63

110/22-15

2002

7

Raising of output of Sai Gon station

20 + 40 --> 2 x 40

110/22-15

2002

8

Raising of output of Ben Thanh station

20 + 63 + 63 --> 2 x 63

110/22-15

2002

9

Raising of output of Phu Dinh station

2 x 40 --> 40 + 63

110/22-15

2004

10

Raising of output of Viet Thanh station

1 x 40 --> 40 + 63

110/22-15

2004

11

An Khanh station (renovated to 110 kV)

1 x 40 --> 1 x 63

110/22-15

2003

12

Xa Lo station (renovated to 110 kV)

2 x 33 +30 + 20 --> 2 x 63

110/22-15

2003

 

New projects:

 

 

 

1

Thanh Da 110 kV station

2 x 40

110/22-15

2002

2

Go Vap 110 kV station

2 x 63

110/22-15

2002

3

Eartern Thu Duc 110 kV station

2 x 40

110/22-15

2002-2004

4

Hoa Hung 110 kV station (GIS)

2 x 63

110/22-15

2002-2003

5

Zoo 110 kV station (GIS)

1 x 63

110/22-15

2003-2004

6

Tan Dinh 110 kV station (GIS)

1 x 63

110/22-15

2004

7

Tao Dan 110 kV station (GIS)

1 x 63

110/22-15

2004

8

Tan Son Nhat 110 kV station (GIS)

1 x 63

110/22-15

2004-2005

9

Binh Chanh 110 kV station

1 x 40

110/22-15

2002-2003

10

Tan Binh 2 110 kV station

2 x 63

110/22-15

2003-2004

11

District 6 110 kV station

1 x 63

110/22-15

2003

12

Vinh Loc 110 kV station

1 x 40

110/22

2002-2003

13

Tam Binh 110 kV station

1 x 40

110/22-15

2003

14

Tan Hung 110 kV station (GIS)

1 x 63

110/22-15

2004-2005

15

Linh Trung 110 kV station

1 x 40

110/22-15

2002-2003

16

Le Minh Xuan 110 kV station

1 x 40

110/22-15

2004

17

Southern Sai Gon 4 110 kV station

1 x 63

110/22-15

2004-2005

18

Cat Lai 110 kV station

2 x 63

110/15

2004-2005

19

Tan Binh 1 110 kV station

1 x 63

110/15

2004-2005

20

Hiep Phuoc 110 kV station

1 x 63

110/22

2004-2005

 

II. 2006-2010 period (forecast):

 

 

 

 

Expansion and output-raising projects:

 

 

 

1

Tao Dan 110 kV station

1 x 63 (transformer 2)

110/22

2006

2

So Thu (Zoo) 110 kV station

1 x 63 (transformer 2)

110/22

2006

3

Tan Dinh 110 kV station

1 x 63 (transformer 2)

110/22

2006

4

Tan Hung 110 kV station

1 x 63 (transformer 2)

110/22

2007

5

Linh Trung 110 kV station

1 x 40 (transformer 2)

110/22

2006

6

Tan Son Nhat 110 kV station

1 x 63 (transformer 2)

110/22

2007

7

District 6 110 kV station

1 x 63 (transformer 2)

110/22

2006

8

Tam Binh 110 kV station

1 x 40 (transformer 2)

110/22

2008

9

Southern Sai Gon 110 kV station No.1

1 x 63 (transformer 2)

110/22

2006

10

Southern Sai Gon 110 kV station No.2

1 x 63 (transformer 2)

110/22

2006

11

Southern Sai Gon 110 kV station No.4

1 x 63 (transformer 2)

110/22

2007

12

Vinh Loc 110 kV station

1 x 40 (transformer 2)

110/22

2007

13

Le Minh Xuan 110 kV station

1 x 40 (transformer 2)

110/22

2008

14

An Khanh 110 kV station

1 x 63 (transformer 2)

110/22-15

2007

15

Phu Hoa Dong 110 kV station

1 x 25 (transformer 2)

110/22

2006

16

Cu Chi 110 kV station

1 x 63 (transformer 2)

110/22

2006

17

Can Gio 110 kV station

1 x 16 --> 1 x 25

110/22

2006

18

Phu Dinh 110 kV station

40 + 63 --> 2 x 63

110/22

2007

19

Sao Mai 110 kV station No.1

9.6

110/6

2007

20

Hiep Phuoc 110 kV station

5 x 63

110/22

2007

21

Binh Chanh 110 kV station

1 x 40 (transformer 2)

110/15

2008

22

Nha Be 110 kV station

2 x 40 --> 2 x 63

110/22

2008

23

Viet Thanh 110 kV station

40 + 63 --> 2 x 63

110/22

2007

24

Chanh Hung 110 kV station

2 x 40 --> 2 x 63

110/22

2006

 

New projects:

 

 

 

1

Binh Hoa 110 kV station

2 x 40

110/22

2006

2

Tan Binh 110 kV station No.3

2 x 63

110/22

2007

3

An Ha 110 kV station

1 x 40

110/22

2009

4

Southern Sai Gon 110 kV station No.3

2 x 63

110/22

2006

5

Go Vap 110 kV station No.2

2 x 63

110/22

2007

6

Tang Nhon Phu 110 kV station

2 x 63

110/22

2008

7

Nha Be Steel 110 kV station

2 x 25

110/6

2007

8

Tan Tao 110 kV station

2 x 63

110/15

2007

9

Sao Mai 110 kV station No.2

9.6

110/6

2010

10

Hoc Mon 110 kV station No.2

2 x 63

110/22

2006-2007

11

Tan Thoi Hiep 110 kV station

1 x 63

110/22

2009-2010

12

Tan Quy 110 kV station

1 x 63

110/22

2009-2010

2. List of transmission lines:

Ordinal number

Names of projects

Tension levels (kV)

Commissioning years

 

I. New projects:

 

 

1

Nha Be - Tao Dan (under ground cable + aerial lines)

220 kV

2003-2004

2

Phu My - Cat Lai

220 kV

2002

3

Cat Lai - Thu Duc

220 kV

2004

4

Cat Lai - Nha Be

220 kV

2005

5

Hoc Mon - Thu Duc (circuit 2)

220 kV

2004

6

Binh Trieu - Thanh Da

110 kV

2002

7

Hoc Mon - Go Vap 1

110 kV

2002

8

Cat Lai - Eastern Thu Duc

110 kV

2003

9

Line to Hoa Hung station

110 kV

2002

10

Nha Be - Viet Thanh (circuit 2)

110 kV

2002

11

Tao Dan - Zoo (underground cable)

110 kV

2002

12

Tao Dan - Tan Dinh (underground cable)

110 kV

2004

13

Tao Dan - Ben Thanh (underground cable)

110 kV

2004

14

Hoa Xa - Tan Son Nhat (underground cable)

110 kV

2005

15

Line to Binh Chanh station

110 kV

2003

16

Line to Tan Binh station No.2

110 kV

2004

17

Line to District 6 station

110 kV

2003-2004

18

Line to Vinh Loc station

110 kV

2002

19

Line to Tam Binh station

110 kV

2003

20

Line to Southern Sai Gon station No.2

110 kV

2003

21

Cat Lai - An Khanh line

110 kV

2003

22

Phu Lam - Le Minh Xuan station line

110 kV

2004

23

Viet Thanh - Tan Thuan line

110 kV

2005

24

Line to Binh Hoa station

110 kV

2006

25

Line to Tan Binh station No.3

110 kV

2007

26

Line to An Ha station

110 kV

2009

27

Line to Go Vap station No.2

110 kV

2007

28

Line to Tang Nhon Phu station

110 kV

2008

29

Line to Sao Mai station No.2

110 kV

2009-2010

30

Line to Hoc Mon station No.2

110 kV

2006-2007

31

Line to Tan Thoi Hiep station

110 kV

2009

32

Line to Tan Quy station

110 kV

2009

 

II. Renovation and upgrading projects:

 

 

1

Thu Duc (Sai Gon) - Xa Lo line

66 kV --> 110 kV

2003

2

Thu Duc (Sai Gon) - Viet Thanh line

66 kV --> 110 kV

2003

3

Nha Be - Viet Thanh (former) 110 kV line

Enlargement of cross-section

 

Đã xem:

Đánh giá:  
 

Thuộc tính Văn bản pháp luật 699/QD-TTg

Loại văn bảnQuyết định
Số hiệu699/QD-TTg
Cơ quan ban hành
Người ký
Ngày ban hành23/08/2002
Ngày hiệu lực23/08/2002
Ngày công báo...
Số công báo
Lĩnh vựcXây dựng - Đô thị
Tình trạng hiệu lựcCòn hiệu lực
Cập nhật16 năm trước
Yêu cầu cập nhật văn bản này

Download Văn bản pháp luật 699/QD-TTg

Lược đồ Decision No. 699/QD-TTg of August 23, 2002, approving the planning on development and renovation of Ho Chi Minh city's power network in the 2002-2010 period, with the prospect till 2020 taken into account


Văn bản bị sửa đổi, bổ sung

    Văn bản sửa đổi, bổ sung

      Văn bản bị đính chính

        Văn bản được hướng dẫn

          Văn bản đính chính

            Văn bản bị thay thế

              Văn bản hiện thời

              Decision No. 699/QD-TTg of August 23, 2002, approving the planning on development and renovation of Ho Chi Minh city's power network in the 2002-2010 period, with the prospect till 2020 taken into account
              Loại văn bảnQuyết định
              Số hiệu699/QD-TTg
              Cơ quan ban hànhThủ tướng Chính phủ
              Người kýNguyễn Tấn Dũng
              Ngày ban hành23/08/2002
              Ngày hiệu lực23/08/2002
              Ngày công báo...
              Số công báo
              Lĩnh vựcXây dựng - Đô thị
              Tình trạng hiệu lựcCòn hiệu lực
              Cập nhật16 năm trước

              Văn bản thay thế

                Văn bản được dẫn chiếu

                  Văn bản hướng dẫn

                    Văn bản được hợp nhất

                      Văn bản hợp nhất

                        Văn bản gốc Decision No. 699/QD-TTg of August 23, 2002, approving the planning on development and renovation of Ho Chi Minh city's power network in the 2002-2010 period, with the prospect till 2020 taken into account

                        Lịch sử hiệu lực Decision No. 699/QD-TTg of August 23, 2002, approving the planning on development and renovation of Ho Chi Minh city's power network in the 2002-2010 period, with the prospect till 2020 taken into account

                        • 23/08/2002

                          Văn bản được ban hành

                          Trạng thái: Chưa có hiệu lực

                        • 23/08/2002

                          Văn bản có hiệu lực

                          Trạng thái: Có hiệu lực