Thông tư 16/2020/TT-BCT

Circular No. 16/2020/TT-BCT dated July 7, 2020 on amendments to Circular No. 44/2015/TT-BCT on development of avoidable cost tariff and sample of electricity sale contract applicable to biomass power projects

Nội dung toàn văn Circular 16/2020/TT-BCT amendments 44/2015/TT-BCT avoidable cost tariff of power projects


MINISTRY OF INDUSTRY AND TRADE
-------

SOCIALIST REPUBLIC OF VIETNAM
Independence – Freedom – Happiness
----------------

No. 16/2020/TT-BCT

Hanoi, July 7, 2020

 

CIRCULAR

AMENDMENTS TO CIRCULAR NO. 44/2015/TT-BCT DATED DECEMBER 9, 2015 OF MINISTER OF INDUSTRY AND TRADE ON DEVELOPMENT OF AVOIDABLE COST TARIFF AND SAMPLE OF ELECTRICITY SALE CONTRACT APPLICABLE TO BIOMASS POWER PROJECTS

Pursuant to Decree No. 98/2017/ND-CP dated August 18, 2017 of the Government on functions, tasks, powers, and organizational structure of the Ministry of Industry and Trade;

Pursuant to Decision No. 24/2014/QD-TTg dated March 24, 2014 of Prime Minister on incentive policies for development of biomass power projects in Vietnam; and Decision No. 08/2020/QD-TTg dated March 5, 2020 of Prime Minister on amendments to Decision No. 24/2014/QD-TTg dated March 24, 2014 of Prime Minister on incentive policies for development of biomass power projects in Vietnam;

At request of Director General of Electricity and Renewable Energy Authority,

Minister of Industry and Trade promulgates Circular on amendments to Circular No. 44/2015/TT-BCT dated December 9, 2015 of Minister of Industry and Trade on development of avoidable cost tariff and sample of electricity sale contract applicable to biomass power projects.

Article 1. Amendments to Circular No. 44/2015/TT-BCT dated December 9, 2015 of Minister of Industry and Trade on development of avoidable cost tariff and sample of electricity sale contract applicable to biomass power projects

1. Amendments to Article 1 are as follows:

“Article 1. Scope

This Circular prescribes development of biomass power projects and samples of electricity sale contract applicable to grid-connected biomass power projects (hereinafter referred to as “sample of electricity sale contract”).”

2. Amendments to Clause 1 Article 5 as follows:

“1. Project developers shall only prepare grid-connected biomass power projects under electricity development planning or approved provincial planning. Details of biomass power investment projects shall be prepared according to applicable regulations and law on management of construction investment and according to Clause 3 of this Article.

3. Amendment to Chapter III title is as follows: “Chapter III. Sample electricity sale contract for grid-connected biomass power projects”.

4. Amendments to Article 9 are as follows:

“Article 9. Application of electricity price for biomass power projects

Electricity price applicable to grid-connected biomass power projects shall conform to Decision No. 08/2020/QD-TTg dated March 5, 2020 of Prime Minister on amendments to Decision No. 24/2014/QD-TTg dated March 24, 2014 of Prime Minister on incentive policies for development of biomass power projects in Vietnam.”

5. Amendments to Clause 1 Article 10 as follows:

“1. Use of sample electricity sale contract for grid-connected biomass power projects is compulsory during electricity sale between the Seller and the Buyer.”

6. Amendments Article 11 are as follows:

“Article 11. Implementation

1. Electricity and Renewable Energy Authority is responsible for:

a) publicizing, guiding and examining implementation of this Circular;

b) difficulties that arise during the implementation of this Circular should be reported to the Ministry for consideration.

2. On a yearly basis, People’s Committees of provinces where biomass power projects are located shall submit written reports using defined form to Ministry of Industry and Trade (via Electricity and Renewable Energy Authority) on investment application and implementation of projects within the provinces for supervision and management before January 15.”

7. Amendments to Point a Clause 2 and Point a Clause 3 Article 12 are as follows:

“Article 12. Responsibilities of relevant organizations and individuals

2. The Seller is responsible for:

a) entering into agreement with the Buyer according to sample electricity sale contract and electricity price specified under Decision No. 08/2020/QD-TTg dated March 5, 2020 of Prime Minister on amendments to Decision No. 24/2014/QD-TTg dated March 24, 2014 of Prime Minister on incentive policies for development of biomass power projects in Vietnam;

3. The Buyer is responsible for:

a) entering into agreement with the Seller according to sample electricity sale contract and electricity price specified under Decision No. 08/2020/QD-TTg dated March 5, 2020 of Prime Minister on amendments to Decision No. 24/2014/QD-TTg dated March 24, 2014 of Prime Minister on incentive policies for development of biomass power projects in Vietnam.”

8. Amendments to Article 13 are as follows:

“Article 13. Transition clauses

Biomass power projects that generate power before April 25, 2020 shall be re-entered via electricity sale contract with the Buyer in order to be applied with electricity price specified under Clause 9 Article 1 Decision No. 08/2020/QD-TTg from April 25, 2020 until the expiry date of the previously entered electricity sale contract.”

9. Add Annex II for Annual report form for reports produced by People’s Committees of provinces on investment application and implementation results of biomass power projects within the provinces as specified under Clause 6 of this Article.

Article 2. Replacement and annulment

1. Replace Annex III attached to Circular No. 44/2015/TT-BCT dated December 9, 2015 of Minister of Industry and Trade on development of avoidable cost tariff and sample of electricity sale contract applicable to biomass power projects with Annex I attached to this Circular.

2. Replace “General Directorate of Energy” under Circular No. 44/2015/TT-BCT dated December 9, 2015 with “Electricity and Renewable Energy Authority”;

3. Annul Clause 4 Article 2, Article 3, Article 4, Clause 2 Article 5, Article 8, Point c Clause 2, Clause 4 Article 12, Annex I, and Annex II under Circular No. 44/2015/TT-BTC dated December 9, 2015;

4. Annul Circular No. 29/2015/TT-BCT dated August 31, 2015 of Minister of Industry and Trade on contents and procedures for preparing, appraising and approving biomass power development and use planning.

Article 3. Entry into force

This Circular comes into force from August 20, 2020.

 

 

PP. MINISTER
DEPUTY MINISTER




Hoang Quoc Vuong

 


------------------------------------------------------------------------------------------------------
This translation is made by THƯ VIỆN PHÁP LUẬT and for reference purposes only. Its copyright is owned by THƯ VIỆN PHÁP LUẬT and protected under Clause 2, Article 14 of the Law on Intellectual Property.Your comments are always welcomed

Đã xem:

Đánh giá:  
 

Thuộc tính Văn bản pháp luật 16/2020/TT-BCT

Loại văn bảnThông tư
Số hiệu16/2020/TT-BCT
Cơ quan ban hành
Người ký
Ngày ban hành07/07/2020
Ngày hiệu lực20/08/2020
Ngày công báo...
Số công báo
Lĩnh vựcThương mại
Tình trạng hiệu lựcCòn hiệu lực
Cập nhật4 năm trước
Yêu cầu cập nhật văn bản này

Download Văn bản pháp luật 16/2020/TT-BCT

Lược đồ Circular 16/2020/TT-BCT amendments 44/2015/TT-BCT avoidable cost tariff of power projects


Văn bản bị sửa đổi, bổ sung

    Văn bản liên quan ngôn ngữ

      Văn bản sửa đổi, bổ sung

        Văn bản bị đính chính

          Văn bản được hướng dẫn

            Văn bản đính chính

              Văn bản bị thay thế

                Văn bản hiện thời

                Circular 16/2020/TT-BCT amendments 44/2015/TT-BCT avoidable cost tariff of power projects
                Loại văn bảnThông tư
                Số hiệu16/2020/TT-BCT
                Cơ quan ban hànhBộ Công thương
                Người kýHoàng Quốc Vượng
                Ngày ban hành07/07/2020
                Ngày hiệu lực20/08/2020
                Ngày công báo...
                Số công báo
                Lĩnh vựcThương mại
                Tình trạng hiệu lựcCòn hiệu lực
                Cập nhật4 năm trước

                Văn bản thay thế

                  Văn bản được dẫn chiếu

                    Văn bản hướng dẫn

                      Văn bản được hợp nhất

                        Văn bản được căn cứ

                          Văn bản hợp nhất

                            Văn bản gốc Circular 16/2020/TT-BCT amendments 44/2015/TT-BCT avoidable cost tariff of power projects

                            Lịch sử hiệu lực Circular 16/2020/TT-BCT amendments 44/2015/TT-BCT avoidable cost tariff of power projects

                            • 07/07/2020

                              Văn bản được ban hành

                              Trạng thái: Chưa có hiệu lực

                            • 20/08/2020

                              Văn bản có hiệu lực

                              Trạng thái: Có hiệu lực