Thông tư 03/2008/TT-BXD

Circular No. 03/2008/TT-BXD of January 25, 2008, guiding the adjustment of work construction cost estimates.

Nội dung toàn văn Circular No. 03/2008/TT-BXD of January 25, 2008, guiding the adjustment of work construction cost estimates.


THE MINISTRY OF CONSTRUCTION

SOCIALIST REPUBLIC OF VIET NAM
Independence Freedom Happiness

 

No. 03/2008/TT-BXD

Hanoi, January 25, 2008

 

CIRCULAR

GLIDING THE ADJUSTMENT OF WORK CONSTRUCTION COST ESTIMATES

Pursuant to the Government's Decree No. 36/2003/ND-CP of April 4, 2003, defining the functions, tasks, powers and organizational structure of the Ministry of Construction;
Pursuant to the Governments Decree No. 16/2005/ND-CP of February 7, 2005, on management of investment projects on the construction of works and Decree No. 112/2006/ND-CP of September 29, 2006 amending and supplementing a number of articles of the Government's Decree No. 16/2005/ND-CP on management of investment projects on the construction of works;
Pursuant to the Governments Decree No. 99/2007/ND-CP of June 13, 2007, on management of work construction investment expenditures;
Pursuant to the Government's Decree No. 03/2008/ND-CP of January 7, 2008, amending and supplementing a number of articles of the Government's Decree No. 99/2007/ND-CP of June 13, 2007, on management of work construction investment expenditures;
Pursuant to the Government's Decree No. 166/2007/ND-CP of November 16, 2007, providing for the common minimum wage level;
Pursuant to the Governments Decree No. 167/2007/ND-CP of November 16, 2007, providing for region-based minimum wage levels for laborers working for Vietnamese companies, enterprises, cooperatives, cooperative groups, farms, households, individuals and other labor-employing organizations;
Pursuant to the Labor, War Invalids and Social Affairs Ministry's Circular No. 29/2007/TT-BLDTBXH of December 5, 2007, guiding the application of the common minimum wage level and region-based minimum wage level in state companies and one-member limited liability companies where the State holds 100% charter capital.
The Ministry of Construction guides the adjustment of work construction cost estimates from January 1, 2008, as follows:

I. GENERAL PROVISIONS

1. This Circular guides the adjustment of cost estimates for the volumes performed from January 1, 2008, under state-funded works or bidding packages (referred to as work construction cost estimates) for which the investment deciders have not yet decided to switch the management of work construction investment expenditures under the Government's Decree No. 99/2007/ND-CP of June 13, 2007.

Work construction investment projects funded with other capital sources are encouraged to apply regulations on adjustment of cost estimates guided in this Circular.

2. Work construction cost estimates formulated using construction, installation and construction survey unit prices set by provinces or centrally run cities on the basis of wage scales of the wage table A.1.8 promulgated together with the Government's Decree No. 205/2004/ND-CP of December 14, 2004, with the minimum wage level of VND 450.000/month, will be adjusted as prescribed in the Appendix to this Circular.

3. For works for which separate unit prices or machine-shift costs have been formulated using the minimum wage level specified by competent persons, work construction cost estimates will be adjusted using the new common minimum wage level or new region-based minimum wage level in accordance with the principles and methods guided in this Circular.

4. Adjustment of contract prices or amounts paid for work volumes performed from January 1, 2008, under signed contracts and contractual terms: If the involved parties have agreed not adjust price- during the implementation process, investors and construction contractors may negotiate and supplement contracts in order to ensure laborers interests as prescribed.

5. For works under work construction investment projects implemented under the Government's Decree No. 99/2007/ND-CP of June 13, 2006, on management of work construction investment expenditures, investors shall use contingency funds for price increase to adjust the expenditure structure in the work construction cost estimates.

II. SPECIFIC PROVISIONS

Work construction cost estimates formulated using construction unit prices set by provinces or centrally run cities on the basis of the minimum wage level of VND 450,000 per month and wage scales in the wage table promulgated together with the Government's Decree No. 205/2004/ND-CP of December 14, 2004, are adjusted as follows:

1. Adjustment of construction cost estimates

1.1. Adjustment of labor expenses

Labor expenses in construction cost estimates formulated using local construction unit prices will be multiplied by an adjustment coefficient (KDC NC) in conformity with the adjustment of the common minimum wage level or region-based minimum wage level.

The adjustment coefficient (KDC NC) is determined as being equal to the new minimum wage level or region-based minimum wage level divided by the minimum wage level used for unit price calculation (VND 450,000/month).

1.2. Adjustment of construction machine expense

Construction machine expenses in construction cost estimates formulated using local construction unit prices will be multiplied by an adjustment coefficient (KDC MTC) in conformity with the adjustment of the common minimum wage level, region-based minimum wage level and fuel and energy prices in January 2008.

The adjustment coefficient (KDC MTC) of construction machine expenses is determined by calculating the weighted average expenses for each group of machines.

According to the above-said principle, the coefficient (KDC MTC) for adjustment of construction machine expenses in construction expense estimates made by provinces and centrally run cities will comply with the enclosed Appendix. The coefficient applicable to provinces or cities with a particular construction structure will be decided by provincial/municipal People's Committees.

For works which are built in lines running through several provinces or centrally run cities for which separate machine-shift price tables have been formulated, investors shall calculate and report adjustment coefficients to investment deciders for decision.

1.3. Expenses calculated in proportion (%) to construction cost estimates

Expenses calculated in proportion (%) to construction cost estimates include: other direct expenses, common expenses, pre-calculated taxable incomes, value added tax amounts, expenses for makeshift houses at construction sites for accommodation or construction administration as prescribed.

2. Some other expenses

Expenses such as those for management of work construction investment projects, project elaboration and construction work designing are calculated in a percentage (%) as prescribed.

Labor expenses in construction survey cost estimates will be adjusted using an adjustment coefficient (KDC NCKS) prescribed in Table 2 in the Appendix to this Circular.

Particularly, pre-tax cost estimates for elaboration of urban construction planning will be determined on the basis of the construction planning expense limits promulgated together with the Construction Minister's Decision No. 06/2005/QD-BXD of February 3, 2005, multiplied by adjustment coefficient KDC QHXD= 1.25.

For cost estimates for provision of urban public services, provincial-level People's Committees shall based themselves on specific local conditions to guide the adjustment.

III. ORGANIZATION OF IMPLEMENTATION

1. For works under work construction investment projects for which investment deciders have not yet decided to switch the management of work construction investment expenditures under the Government's Decree No. 99/2007/ND-CP of June 13, 2006:

1.1. Provincial/municipal People's Committees shall, based on the guidance in this Circular and regulations on the minimum wage level, region-based minimum wage level and wage-based allowances, guide the adjustment of work construction cost estimates of state-funded construction works.

Provincial/municipal Construction Services shall assume the prime responsibility for, and coordinate with concerned local agencies in, determining adjustment coefficients for submission to provincial/municipal People's Committees for promulgation and application.

1.2. Ministries, economic groups and state corporations shall guide the adjustment of work construction cost estimates of work construction investment projects under their investment decision competence under the guidance of this Circular.

1.3. Investors shall organize and approve the results of adjustment of work construction cost estimates in accordance with, current regulations.

1.4. For construction works for which separate unit prices have been formulated (work construction unit prices), investors shall base themselves on regimes and policies permitted by the State for application and the principles of adjustment of work construction cost estimates guided in this Circular to determine the levels of adjustment of labor expenses, construction machine expenses and other expenses (if any) in work construction cost estimates.

2. For works of work construction investment projects implemented under the Governments Decree No. 99/2007/ND-CP of June 13, 2007, on management of work construction investment expenditures, their cost estimates shall be adjusted under the guidance at Point 4, Section I, of this Circular.

This Circular takes effect 15 days after its publication in "CONG BAO."

 

FOR THE MINISTER OF CONSTRUCTION
VICE MINISTER




Dinh Tien Dung

 

 

APPENDIX
(Attached to the Construction Minister's Circular So. 03/2008/TT-BXD of January 25, 2008)

To adjust work construction cost estimates formulated using construction, installation and construction survey unit prices determined by provinces or centrally run cities (on the basis of wage scales of wage table A.1.8. promulgated together with the Government's Decree No. 205/2004/ND-CP of December 14, 2004, with the minimum wage level of VND 450,000/month) before the effective date of the Government's Decree No. 99/2007/ND-CP of June 13, 2006, on management of work construction investment expenditures:

1. Adjustment of construction cost estimates

1.1. Adjustment of labor expenses and construction machine expenses

Labor expenses and construction machine expenses in construction cost estimates will be multiplied by the adjustment coefficients (KDC NC) and (KDC MTC) prescribed in Table 1 of this Appendix.

1.2. Expenses calculated in proportion (%) to construction cost estimates.

Other direct expenses, common expenses, pre-calculated taxable incomes, value-added tax amounts and expenses for construction of makeshift houses at construction sites for accommodation and construction administration will be calculated in a percentage as prescribed.

2. Adjustment of other expenses

2.1. Adjustment of construction survey cost estimates

Labor expense in construction survey cost estimates will be multiplied by the adjustment coefficient (KDC NCKS) prescribed in Table 2 of this Appendix.

2.2. Adjustment of labor expenses in cost estimates for testing construction materials and structure.

Labor expenses in cost estimates for testing materials and construction structure determined using norms and unit prices for testing materials and construction structure promulgated together with the Construction Minister's Decision No. 32/2001/QD-BXD of December 20,2001, will be multiplied by the adjustment coefficient (KDC NCTN) prescribed in Table 3 of this Appendix.

2.3. Other expenses which are calculated in proportion (%) to work construction cost estimates will be calculated according to current regulations of the State.

Table I. Coefficients for adjustment of construction cost estimates

Minimum wage level

VND 540,000/month

VND 580,000/month

VND 620,000/month

Adjustment coefficient KDC NC

1.20

1.29

1.378

Adjustment coefficient KDC MTC

1.08

1.1

1.12

Table 2. Coefficients for adjustment of construction survey cost estimates

Minimum wage level .

VND 540,000/month

VND 580,000/month

VND 620,000/month

Adjustment coefficient KDC NCKS

1.20

1.29

1.378

Table 3. Coefficients for adjustment of cost estimates for testing materials and construction structure

Minimum wage level

VND 540,000/month

VND 580,000/month

VND 620,000/month

Adjustment coefficient KDC NCTN

2.83

3.04

3.25

 

Đã xem:

Đánh giá:  
 

Thuộc tính Văn bản pháp luật 03/2008/TT-BXD

Loại văn bảnThông tư
Số hiệu03/2008/TT-BXD
Cơ quan ban hành
Người ký
Ngày ban hành25/01/2008
Ngày hiệu lực24/02/2008
Ngày công báo...
Số công báo
Lĩnh vựcXây dựng - Đô thị
Tình trạng hiệu lựcCòn hiệu lực
Cập nhật18 năm trước
Yêu cầu cập nhật văn bản này

Download Văn bản pháp luật 03/2008/TT-BXD

Lược đồ Circular No. 03/2008/TT-BXD of January 25, 2008, guiding the adjustment of work construction cost estimates.


Văn bản bị sửa đổi, bổ sung

    Văn bản sửa đổi, bổ sung

      Văn bản bị đính chính

        Văn bản đính chính

          Văn bản bị thay thế

            Văn bản hiện thời

            Circular No. 03/2008/TT-BXD of January 25, 2008, guiding the adjustment of work construction cost estimates.
            Loại văn bảnThông tư
            Số hiệu03/2008/TT-BXD
            Cơ quan ban hànhBộ Xây dựng
            Người kýĐinh Tiến Dũng
            Ngày ban hành25/01/2008
            Ngày hiệu lực24/02/2008
            Ngày công báo...
            Số công báo
            Lĩnh vựcXây dựng - Đô thị
            Tình trạng hiệu lựcCòn hiệu lực
            Cập nhật18 năm trước

            Văn bản thay thế

              Văn bản hướng dẫn

                Văn bản được hợp nhất

                  Văn bản gốc Circular No. 03/2008/TT-BXD of January 25, 2008, guiding the adjustment of work construction cost estimates.

                  Lịch sử hiệu lực Circular No. 03/2008/TT-BXD of January 25, 2008, guiding the adjustment of work construction cost estimates.

                  • 25/01/2008

                    Văn bản được ban hành

                    Trạng thái: Chưa có hiệu lực

                  • 24/02/2008

                    Văn bản có hiệu lực

                    Trạng thái: Có hiệu lực