OFFICIAL DISPATCH

GUIDING THE INVESTMENT PROCEDURE ON CONSTRUCTION OF WORKS

To: The Financial Administration Department - The Ministry of Foreign Affairs

Ministry of Construction received the document No. 389/BNG-QTTV on June 22, 2010 of the Financial Administration Department - The Ministry of Foreign Affairs proposing the Ministry of Finance guiding the approvals on adjusting working drawings design. After studying, the Ministry of Construction has opinions as follows:

According to regulations at Article 18 of the Decree No. 12/2009/ND-CP dated February 12, 2009 of the Government on management of investment projects on the construction of works: Working drawing designs must be certified by investors or their authorized representatives In case of two-step or three-step designing.

To regulations at clause 4, Article 1 of the Decree No. 49/2008/ND-CP dated April 18, 2008 of the Government amending and supplementing a number of articles of the Government's Decree No. 209/2004/ND-CP dated December 16, 2004, on quality management of construction works “...Construction-supervising contractors may sign and adjust in construction drawing designs the contents already approved by investors and shall bear responsibility for their decisions." Therefore, in the case of changing working drawing design in the construction process, the investor will be responsible for approving to adjust working drawing designs or accept all contents need to be adjusted so that construction-supervising contractor can sign in the working drawing design. Investor can authorize the Project Management Board to adjust working drawing design.

Opinions of the Ministry of Construction as above, the Financial Administration Department - The Ministry of Foreign Affairs shall study and implement right to these regulations./.

 

 

FOR THE MINISTER OF CONSTRUCTION
MANAGER OF MANAGEMENT DEPARTMENT OF CONSTRUCTION ACTIVITIES




Tran Ngoc Thien

 

 

Đã xem:

Đánh giá:  
 

Thuộc tính Công văn 69/BXD-HDXD

Loại văn bản Công văn
Số hiệu 69/BXD-HDXD
Cơ quan ban hành
Người ký
Ngày ban hành 12/07/2011
Ngày hiệu lực 12/07/2011
Ngày công báo ...
Số công báo
Lĩnh vực Xây dựng - Đô thị
Tình trạng hiệu lực Không xác định
Cập nhật 14 năm trước
Yêu cầu cập nhật văn bản này

Download Công văn 69/BXD-HDXD

Lược đồ Official Dispatch No. 69/BXD-HDXD guiding the investment procedure on constructi


Văn bản bị sửa đổi, bổ sung

Văn bản sửa đổi, bổ sung

Văn bản bị đính chính

Văn bản được hướng dẫn

Văn bản đính chính

Văn bản bị thay thế

Văn bản hiện thời

Official Dispatch No. 69/BXD-HDXD guiding the investment procedure on constructi
Loại văn bản Công văn
Số hiệu 69/BXD-HDXD
Cơ quan ban hành Bộ Xây dựng
Người ký Trần Ngọc Thiện
Ngày ban hành 12/07/2011
Ngày hiệu lực 12/07/2011
Ngày công báo ...
Số công báo
Lĩnh vực Xây dựng - Đô thị
Tình trạng hiệu lực Không xác định
Cập nhật 14 năm trước

Văn bản thay thế

Văn bản được căn cứ

Văn bản hợp nhất

Văn bản gốc Official Dispatch No. 69/BXD-HDXD guiding the investment procedure on constructi

Lịch sử hiệu lực Official Dispatch No. 69/BXD-HDXD guiding the investment procedure on constructi

  • 12/07/2011

    Văn bản được ban hành

    Trạng thái: Chưa có hiệu lực

  • 12/07/2011

    Văn bản có hiệu lực

    Trạng thái: Có hiệu lực